Downtown Update from Brad Curtis – July 2nd
FORT MORGAN DOWNTOWN INFRASTRUCTURE UPDATE (July 2, 2009)
Below is a summary of activities, and not to be considered all inclusive.
1. ECI has reported that after the first 33 construction days the project is on schedule.
2. No work is scheduled for July 3rd, 4th, or 5th.
3. There will be intermittent water service disruptions along Main St. from Beaver to Railroad.
4. Activities worked this week:
- Installed 480′ of 24″ RCP storm pipe, inlet connections and manholes along Main Street to Kiowa.